Five things come out or get broken on almost every pool refurbishment: the perimeter bonding wire, the pool lights, the handrails, the wall return jets, and — if nobody plugs the pipes — the filtration equipment. Four of those are predictable and should be in the scope. The fifth is avoidable and is the most expensive of the lot.

None of this is exotic. It is the part of a pool quote that gets left off, argued about in week three, and then paid for anyway.

Which items always have to come out?

The handrails, the pool lights and the wall return jets come out on every refurbishment, and they come out at different points in the schedule for different reasons.

Handrails come off at the very start and get set aside carefully. If they stay in place through demolition they end up smeared with adhesive, epoxy and cement, and cleaning them costs more than removing them would have. The metal anchor sockets stay in the deck — they are already dimensioned to the existing deck thickness, and this isn’t a new pool. Work around them, bond up to them, leave them alone.

If the handrails are in good condition, they go back. Do not replace them. That is the client’s money and there is nothing wrong with them.

Wall return jets are the opposite: they stay in place almost to the end, because they are not at risk during the rough work and they need replacing anyway. They get pulled immediately before the finish goes on and reinstalled immediately after. A jet set belongs in the price.

Pool lights are the ones that eat the time. The lens comes off carefully at the start and the fitting is masked and isolated. The finish runs up around the light, never over it — the fixture has a purpose-made niche already cast into the concrete and its own rubber gasket, which is what makes the water seal. There is no membrane behind the lamp; the gasket does that job.

The timing on lights is unforgiving. They go back in the moment the finish is complete, because the pool is filled the same day — otherwise you are diving and fitting lamps underwater.

Why does the bonding wire always get broken?

The copper equipotential bonding wire runs the full perimeter of the pool under the deck tile, and it will almost certainly be torn during demolition. Sometimes it is cast into the concrete, which makes it effectively impossible to save. Last time we saved it. The time before that we tore it.

It is a copper conductor that runs right around the pool, comes in at a point, and drops to a ground connection with a dedicated bolt. Lift the deck tile and you will find it.

The fix is straightforward: buy copper wire, re-run it through the existing purpose-made studs and clips, and run it around the perimeter back to the ground bolt. The bolts and fixings stay where they are.

What is not optional is showing it. Everyone asks to see it — they all say, show me that the wire is there. Treat it as an inspection item and photograph it before the deck goes back, because once the paving is down nobody can verify it without lifting the paving again.

What is the one thing that should never get damaged?

The filtration equipment — and the way it gets destroyed is debris going down an unplugged pipe. Once the tile and the grates come off, every drain and suction outlet gets a cut foam plug sealed into it before any chipping starts.

The reason is blunt. Debris and pebbles fall in, travel down the pipes, reach the filter, and the equipment is finished. And the equipment isn’t cheap.

Foam is the best plug. Backer rod works. Rags and bags work. Whatever it is, just remember it’s there — a plug left in at fill time is its own problem.

This is the highest-consequence, lowest-cost step in the entire job. Ten dollars of foam against a filter replacement.

The openings themselves stay open through the work. The waterproofing stops around the penetration rather than running into it, and the hole is never covered over.

What about the depth markers and the step nosings?

Photograph the existing depth markers before demolition so they go back in the same positions. They are ready-made ceramic tiles — “5 FT 6 IN” and so on — set around the perimeter on the coping and on the vertical face inside the pool so they can be read from the water. A square gets cut out with a grinder to seat each one. If nobody photographed the original layout, somebody is guessing at depths, and that is not a thing to guess at.

Step nosings are a safety item, not a design choice. Every step gets a contrast nosing tile — 3.25 inches on the tread, 2 inches down the riser — in a colour that contrasts with the surrounding surface. Light pool, dark blue or black nosing. Dark pool, white. It has to be visible.

All horizontal surfaces in the pool, steps included, get the anti-slip textured tile. Ordinary tile is fine on verticals.

What should be in the scope and usually isn’t?

ItemWhen it happensIn most quotes?
Handrail removal and reinstatementStart and endSometimes
New wall return jet setImmediately before and after the finishOften missed
Pool light removal and reinstatementStart, and same day as the finishSometimes
Perimeter bonding wire replacementAfter demolition, before the deck closesUsually missed
Drain and suction outlet pluggingAfter demolition, before chippingRarely stated
Depth marker reinstatementWith the finishOften missed
Debris removal and haulThroughoutUnder-priced

That last one is worth a note. Debris comes out of a pool in bags, on somebody’s back. On one job the haul distance was long enough that we were running carts nearly half a kilometre to the dumpster. Access and haul distance is a real cost and it is not in anybody’s square-foot rate — it should be priced separately, and a property manager should expect to be asked where the bin can go.

What most people get wrong

Assuming these items are included because they are obviously necessary. They are necessary. They are frequently not in the number.

The bonding wire is the clearest example. Everybody wants to see it, almost nobody prices it, and it is the one thing that cannot be verified after the deck closes. Ask about it at tender, not at handover.

What to do about it

Before the pool closes, walk it with the contractor and photograph five things: the depth marker positions, the handrails in place, the light fittings, the deck tile at the point where the bonding wire enters, and the drains. That set of photographs is what the reinstatement gets checked against, and it takes ten minutes.

Then ask one question at tender: which of the items in the table above are in this price. The answers will differ between bidders, and that difference is usually most of the gap between their numbers.

Book an inspection and we will tell you what has to come out and go back before the price is set, rather than after.

More on swimming pool repair and waterproofing, concrete surface repair and utility and mechanical room waterproofing, or read what the schedule looks like week by week.

See the work. Pool projects: Concrete Repairs and Waterproofing — Multi-Phase Project · Pool Deck Restoration and Waterproofing. More in our projects.

Common questions

Frequently asked questions

Do the pool handrails have to be replaced during a refurbishment?

No — if the handrails are in good condition they come out, get stored, and go back on the original bolts. The anchor sockets stay set in the deck because they are already dimensioned to the existing deck thickness. Replacing sound handrails is spending the corporation's money for nothing; what does need doing is removing them before demolition so they do not get smeared with epoxy and cement.

What happens if the drain pipes are not plugged before demolition?

Debris and small pieces of concrete fall into the open drains and suction outlets, travel down the pipework and reach the filter, and the filtration equipment is destroyed. It is one of the more expensive avoidable outcomes on a pool job, and it is prevented by cut foam plugs sealed into every pipe as soon as the grates come off.

Why does the pool bonding wire matter?

The copper bonding conductor runs around the full perimeter of the pool and connects back to a ground bolt, and it is almost always torn during deck demolition because it is buried under the tile and sometimes cast into the concrete. It has to be re-run through the existing studs and reconnected. Ask to see and photograph it before the deck paving goes back, because after that it cannot be verified without lifting the paving.

Are the pool lights reinstalled before or after the pool is filled?

Before, and the window is tight. The finish is flooded the same day it is applied because it has to cure under water, so the light fittings have to be back in and sealed before the fill starts. Miss the window and the lamps get fitted underwater, which is slower, worse, and entirely avoidable with a schedule that accounts for it.

How do we make sure the depth markers go back in the right places?

Photograph them before demolition. The markers are ready-made ceramic tiles set into cut recesses on the coping and on the inside face of the pool, and once the surface is stripped there is nothing left to indicate where they were. A photo set taken before the first chipping gun starts is the only reliable record.

Is any of this reinstatement work something the building's own staff can do?

Reinstating handrails on existing bolts is straightforward. The bonding wire, the light fittings and anything touching the pipework are not — the bonding conductor is an electrical safety element, the light niches carry the water seal in their own gasket, and an unplugged or wrongly plugged pipe puts the filtration plant at risk. Those belong with the contractor and should be named in the scope.